The eHaus Otago team have been making good progress onsite at Dunedin High Street Co-housing Passive House project. The first three High Street unit roofs are up and all the SIPs (Structural Insulated Panels) have now been installed on the High Street units.
The uPVC (unplasticised polyvinyl chloride) triple glazed windows have all been installed on the ground and first floors of the High Street units.
The eHaus Otago team are now working on standing the SIPs (Structural Insulated Panels) on the Alva Street units. The final concrete pad has been poured for the Alva Street units.